Tuesday, November 1, 2011

Last of the work schedules to finish up projects

We had an amazing weekend with the building project. So many tasks have been completed and the back of the building looks great. Thanks to all who came out! It was a fun weekend working...awesome teamwork!! Here are the remaining work dates and tasks to get done before our first service on November 13:

Wednesday, November 2 (5-9pm)- carpeting in Elem. Theater, Welcome Center and work room; cleaning main baths
Saturday, November 5 (8-2pm, lunch at noon) - carpet in café, move chairs into auditorium, clean doors and windows, water new sod and shrubs, pick up outside site
Wednesday, November 9 (5-9pm) - move chairs into classrooms, finish all cleaning, install any last carpet and base in building
Saturday, November 12 (8-Noon)- finish any tasks if needed

No comments: