We had an amazing weekend with the building project. So many tasks have been completed and the back of the building looks great. Thanks to all who came out! It was a fun weekend working...awesome teamwork!! Here are the remaining work dates and tasks to get done before our first service on November 13:
Wednesday, November 2 (5-9pm)- carpeting in Elem. Theater, Welcome Center and work room; cleaning main baths
Saturday, November 5 (8-2pm, lunch at noon) - carpet in café, move chairs into auditorium, clean doors and windows, water new sod and shrubs, pick up outside site
Wednesday, November 9 (5-9pm) - move chairs into classrooms, finish all cleaning, install any last carpet and base in building
Saturday, November 12 (8-Noon)- finish any tasks if needed
No comments:
Post a Comment