Saturday, October 22, 2011

More Carpet Today!!


Carpet in the classrooms is now complete!!! Way to go, Saturday Team!!

Wednesday, October 19, 2011

First Service - November 13

Our first service is approaching. Last weekend during our worship services, we announced the first 10:00am service will be on Sunday, November 13. That allows us less than a month to get the last building tasks completed. Our original target date for completion was October 30 and we'll still keep that from a sub-contractor and volunteer work perspective. We have two weeks of work dates this week and next.

This week on site, here is the work to be done....
  • Paving the parking lot
  • Retaining wall completed
  • Concrete patio poured
  • Carpet in 3 of the classrooms
  • Plumbing and bath fixtures finished
With every passing day, it becomes clearer to see how incredible the new space will be for the youth. Both MS and HS youth groups are eager with anticipation of opening the building!!

Monday, October 17, 2011

Work Days this week

We have two last weeks for work days. We're cleaning the site, putting in carpet, putting on outlet plates and other finishing touches. Here are the times volunteers can come out.

5-9pm Tuesday
5-9pm Wednesday
6-9pm Friday
8-Noon Saturday

New Pictures!!

Check out our new pictures! See the slideshow on the right side of the blog. Answers to prayer. Carpet and chairs are on site. Granite counter tops are in and are awesome! Most of the room lighting is in the auditorium. We are ready to lay carpet this week, volunteers!!