Our first service is approaching. Last weekend during our worship services, we announced the first 10:00am service will be on
Sunday, November 13. That allows us less than a month to get the last building tasks completed. Our original target date for completion was October 30 and we'll still keep that from a sub-contractor and volunteer work perspective. We have two weeks of work dates this week and next.
This week on site, here is the work to be done....
- Paving the parking lot
- Retaining wall completed
- Concrete patio poured
- Carpet in 3 of the classrooms
- Plumbing and bath fixtures finished
With every passing day, it becomes clearer to see how incredible the new space will be for the youth. Both MS and HS youth groups are eager with anticipation of opening the building!!