- Duct work running everywhere! The furnace and AC units are being worked on. Lots of that infrastructure is getting placed.
- More interior walls framed; the children's theater is really taking shape.
- Lots of insulation installed and sheetrock hung; the auditorium walls are taking shape and a couple of classrooms in the back of the building are almost entirely sheetrocked.
- Soffit and facia around the edge of the roof is going up.
- Electrical wiring is everywhere; boxes and wires are showing up in rooms with walls.
- Some brick has started going on a couple places around the building.
Thursday, June 23, 2011
Progress in Week D
Great week from our team, which came from five different states. Thanks to Erwin, Scott, Todd, Chris, Kim, Bill, the Jeffcoat team and the rest for all you did this week. You even got to experience some WI spring as it was in the 50's today! I realize this is an incomplete list but as I walk around the site...this is the progress I noticed Week D accomplished!